Download PDFOpen PDF in browserBuffer Based CCPM Scheduling:A Modern Approach for Indian Constraints10 pages•Published: July 22, 2017AbstractAt present in Indian Construction, large number of construction projects is delayed by many reasons one of them is ‘improper planning and scheduling’ and ‘resources uncertainty’, which are more concerned for every project manager. There are many scheduling techniques but resource based technique is only one i.e. Critical chain project management (CCPM). This paper contains review of 35 research papers, thesis and articles on CCPM. Main aim of paper is to explore the opportunities to apply CCPM by means of literature review to minimize uncertainty and variation in project activity duration. Paper also describe theories behind CCPM network and procedure of preparing CCPM network.Keyphrases: buffer management, critical chain project management, resource based scheduling, theory of constraints In: C. D. Modhera, G. J. Joshi, D.P Soni, Indrajit N. Patel, A. K. Verma, L. B. Zala, S. D. Dhiman, D. R. Bhatt, Jagdish M. Rathod, Bhargav C. Goradiya, Mehfuza S. Holia and Dharita K. Patel (editors). ICRISET2017. International Conference on Research and Innovations in Science, Engineering and Technology. Selected Papers in Civil Engineering, vol 1, pages 291-300.
|